Oxygen Towers - Construction Update
Oxygen Towers - Construction Update
 
  • Early works contract started on site 15th May 2017
  • Official ground breaking ceremony took place on the 17th May 2017.
  • The site strip has commenced, removing the substructure material to provide a uniform level across the site
  • Next site activity is the delivery of the piling material which will take 2 – 3 weeks
  • Piling rig being delivered to site for the commencement of the CFA piling in 4 weeks’ time.
  • Piling will take approximately 10 – 12 weeks to complete.
6 June 2017